Research / Energy & Power
Energy & Power
U.S. electricity demand is growing again, and data centers are emerging as the main driver. This page follows the evidence from forecasts to prices, the interconnection queue, the wires and the fuel, and asks three questions: where is the system tightest, what are prices signaling, and who bears the cost if forecasts run high?
01 / 12
Demand: forecasts are rising faster than sales
Sales are growing again. Grid forecasts for the next decade have grown much faster, and they are being revised in both directions.
After a long plateau, U.S. electricity use is rising again. EIA reports retail sales of 4,080 terawatt-hours in 2025, up from 3,975 in 2024, and its short-term outlook forecasts 4,171 for 2026 and 4,232 for 2027. In the 2026 Annual Energy Outlook, EIA says demand rose 2.1% a year over the past five years and projects 0.9%–1.6% a year through 2050, and says data center load “is emerging as the dominant driver of long-term U.S. electricity growth.”
Commercial customers now buy more power than households. In the 12 months to August 2026, commercial sales were 1,536.9 TWh against 1,526.4 TWh residential (2026 months are preliminary).
Grid planners have moved further. NERC now expects summer peak demand across North America to rise by 224 GW over 10 years, up from 132 GW a year earlier and over 80 GW in the 2023 assessment. These are sums of NERC assessment areas, including Canada, not U.S.-only figures. In PJM, each annual forecast has raised the 10-year increase, from about 12 GW in the 2023 report to about 66 GW in the 2026 report.
The 2026 report also cut the near term: PJM says it is “lower than the 2025 Long-Term Load Forecast in the near term through 2032 due to updates to the electric vehicle forecast, economics and large load adjustments.” Both can be true because the windows differ and because later years now carry more large-load growth. For data-center demand ranges from LBNL and the IEA, see our AI & Compute page.
Forecasts are rising faster than delivered sales. In our view, the gap between what planners expect and what customers have committed to is the main uncertainty on this page; sections 04 and 10 show how regulators are trying to narrow it.
01 · Demand
Each PJM forecast has raised the 10-year outlook
PJM RTO summer peak: forecast increase over each report’s 10-year horizon, GW, by report year.
02 / 12
Prices: a capacity market at its cap
PJM’s forward capacity price has hit its cap three times. Texas showed almost no shortage pricing in 2025. The two measure different things.
PJM, the grid operator for much of the Mid-Atlantic and Midwest, runs an auction that buys capacity ahead of each delivery year. Its RTO price rose from $28.92 per MW-day for 2024/25 to $269.92 for 2025/26. A price collar (cap $256.75, floor $138.25 per MW-day ICAP; about $325–$333 and $175–$180 in UCAP terms) applied to the 2026/27–2028/29 auctions, and all three cleared at the cap: $329.17, $333.44 and $325.00.
Even at the cap, the 2028/29 auction procured 6,831.3 MW less than PJM’s reliability requirement, close to the prior auction’s 6,516 MW. PJM’s own reading: “Such a shortage does not necessarily mean that the PJM system will be unable to serve load reliably… it means that PJM would have to operate with slimmer reserves.” Under the tariff, a shortfall of more than one percentage point below the target for three auctions in a row triggers a Reliability Backstop Auction; 2028/29 was the second in a row.
Texas shows a different pattern. ERCOT’s market monitor reports that its real-time shortage adder (ORDC) added about $0.02/MWh on average in 2025, the lowest since 2014, as solar and battery additions raised reserves. The all-in price rose from almost $34 to $38/MWh (+13.8%), driven mainly by a 61% rise in gas prices, not scarcity. Since real-time co-optimization went live on December 5, 2025, shortage pricing is embedded in energy prices, so this adder series ends in 2025.
We do not chart wholesale energy prices side by side. EIA’s republished ICE hub data trade different products at the two hubs (PJM West real-time peak, ERCOT North 345 kV peak), and the ERCOT North series has no trades after 2019, so a fair comparison is not possible from that source.
Inference The two largest data-center regions price scarcity differently. PJM’s forward capacity auction has cleared at its cap three times; ERCOT’s energy-only market showed almost no realized shortage pricing in 2025. The two numbers measure different things (a forward capacity price vs. realized real-time adders), and ERCOT’s monitor warns the current surplus could erode quickly as large loads connect.
02 · Prices
PJM’s capacity price has cleared at its cap three auctions in a row
PJM Base Residual Auction, RTO clearing price by delivery year, $/MW-day of unforced capacity (UCAP).
03 / 12
Interconnection: the queue is long, and most of it never gets built
Supply additions depend on getting through the queue. Historically, about one in eight requested megawatts has made it.
New supply has to pass through an interconnection queue before it can run. LBNL finds that “only 13% of capacity that submitted interconnection requests from 2000-2020 had reached commercial operations by the end of 2025;” 75% was withdrawn and 10% is still active. That makes 13% a lower bound.
The queue itself is changing mix. At the end of 2025, more than 2,060 GW was actively seeking connection. Active natural gas capacity rose 86% to 253 GW in 2025, while solar, storage and wind fell.
A long queue is not a supply pipeline. In our view, a completion rate of about one in eight (13%), by capacity, is the right discount to apply when reading any headline queue total.
03 · Interconnection
Most capacity that asks to connect never gets built
Status at end-2025 of generation and storage capacity that requested interconnection, by request year, % of MW.
Share of 2000–2020 requests operating by end-2025, by type (MW)
| Resource type | Operating |
|---|---|
| Natural gas | 17% |
| Nuclear | 18% |
| Wind | 16% |
| Solar | 11% |
| Solar+Battery | 9% |
| Battery | 7% |
BisonByte calculation from the LBNL project-level file. Lower bound: some capacity is still active.
04 / 12
Large loads: the requests far exceed what will connect
Texas and federal regulators are sorting real projects from speculative ones, and rewarding loads that can be flexible.
ERCOT paused approvals to energize new data centers and crypto-mining loads of 75 MW or more (Aug 3, 2026) pending a verification audit; provisional Batch Zero classification (Sep 3, 2026): 66.4 GW base, 127.9 GW studied, 302.2 GW excluded (BisonByte sum ≈497 GW).
ERCOT’s November community-impact survey drew responses covering about 177 GW of requested capacity; 33 projects each requesting more than 1 GW together account for 36% of requested capacity, and West Texas holds 41%. ERCOT is targeting a final report on December 10, 2026.
Federal rules are moving too:
Flexible loads
Several rule changes would let large loads connect sooner if they agree to curtail. FERC’s June orders list “new transmission services for flexible large loads” among five reform areas, and the DOE proposal asks whether flexible loads could be studied within 60 days. In Texas, Senate Bill 6 (2025) created a Large Load Demand Management Service; ERCOT’s market monitor expects its rulemaking to finish in 2026. In PJM, a September 2025 proposal for “non-capacity-backed load” (new large loads that would not pay for capacity and could be curtailed before capacity-backed demand response) was described as withdrawn by Maryland’s Office of People’s Counsel in October 2025; in January 2026 the PJM Board directed work on a “Connect and Manage” approach instead: new large loads that do not bring their own new generation would be curtailed before emergency demand response when load shed is needed, loads that do bring generation get an expedited interconnection track, and PJM is to start a reliability backstop procurement.
Request totals mix firm projects with speculative ones. In our view, the share that survives verification, not the headline request, is the number that matters for forecasts and for who pays (section 10).
04 · Large loads
Most of Texas’s large-load requests did not qualify for the first study
ERCOT Batch Zero: provisional classification of large-load requests, GW, as of September 3, 2026.
05 / 12
Transmission: fewer high-voltage miles
Line additions fell by more than half in 2025, mostly at the highest voltages.
New generation and new loads both need wires. FERC staff count 782.9 miles of new transmission completed in 2025, less than half of the 1,697.4 miles in 2024. The drop is concentrated at the highest voltages: 500 kV-class additions fell from 554.0 miles to 1.8, while 345 kV rose from 352.1 to 400.8.
FERC staff list 1,838.4 miles as high-probability additions through May 2028, out of 2,202.4 miles proposed.
Line miles are a blunt measure, but the direction matters. In our view, high-voltage transmission is the slowest piece to change, so it is likely to set where large loads can connect first.
05 · Transmission
High-voltage line additions fell sharply in 2025
Miles of new U.S. transmission lines completed by voltage class, 2024 and 2025, and high-probability additions through May 2028.
06 / 12
Grid equipment: long waits, higher prices
Transformer lead times are quoted in years, and producer prices have nearly doubled since 2020.
Large power transformers are a common bottleneck. The Department of Energy reported in 2024 that lead times have become exceptionally long, “with 36-month lead times being commonly quoted and maximum lead times reaching as much as 60 months.” The National Infrastructure Advisory Council cited Wood Mackenzie data showing average transformer lead times rising from about 50 weeks in 2021 to about 120 weeks in 2024, and 80–210 weeks for large substation and generator step-up units (Wood Mackenzie data as cited by NIAC).
No free public series tracks lead times month by month, so the chart shows the closest official proxy: producer prices. The index rose from 255.5 in January 2020 to 483.9 in October 2026 (preliminary). Copper is another input: USGS estimates U.S. net import reliance at 57% of consumption in 2025.
Three turbine makers each report record order books, on definitions that are not comparable (with or without reservations, steam turbines, or frame size), so we do not compare them. Section 09 uses EIA’s plant-level data instead.
Higher prices and long waits point the same way. In our view, equipment, not only permits, will pace how fast new lines and substations arrive.
06 · Grid equipment
Transformer producer prices are up about 89% since January 2020
BLS Producer Price Index, power, distribution and specialty transformer manufacturing (PCU335311335311), monthly, January 2018 to October 2026.
07 / 12
Fuel: gas carries the load, and LNG competes for it
Gas makes about 40% of U.S. power. Exports are rising at the same time, and pipelines set how fast supply can move.
Natural gas is the largest source of U.S. power. EIA puts its share of generation at 39.9% in 2025 and forecasts close to 40% in 2026 and 2027. Gas burned for power has held around 36–38 Bcf/d since 2024, while LNG exports rose from 11.9 Bcf/d in 2024 to 15.1 in 2025 and 17.3 so far in 2026. Henry Hub averaged $2.19 in 2024 and $3.53 in 2025.
EIA’s November outlook expects LNG exports of 19.0 Bcf/d in 2027 and a Henry Hub price near $2.88 in 2027, down from about $3.37 in 2026.
Pipelines are the delivery constraint. EIA’s pipeline project list shows 35 projects under construction (33 with stated capacity), with a sum of stated additional capacity of about 41 Bcf/d, and 13 on hold.
Power demand and LNG exports are now pulling on the same supply. In our view, gas prices, not scarcity, explained most of the 2025 rise in Texas power costs, and the same link will shape costs elsewhere.
07 · Fuel
Power and LNG are both drawing more gas
U.S. natural gas burned for power and LNG exports, Bcf/d (bars), and Henry Hub spot price, $/MMBtu (line), annual averages.
08 / 12
Nuclear: restarts first, new reactors later
A complete list of restarts under NRC review and of 2026 construction permits, with the approval steps each has passed.
Nuclear supply can grow three ways: uprates, restarts and new reactors. The table lists every power-reactor restart under NRC review and every construction permit the NRC issued in 2026. One restart has loaded fuel; a second has a final environmental assessment, with the NRC’s restart decision expected in 2027 for the 800-plus megawatt unit.
Fuel is a constraint for many advanced designs. DOE says “HALEU is not currently available from domestic suppliers.” It has made conditional allocations of high-assay low-enriched uranium in three rounds: April 9, 2025 (5 recipients), August 26, 2025 (3) and July 23, 2026 (2, including NASA).
EIA’s plant-level data show planned nuclear additions of 0.5 GW in 2030 and 2.2 GW in each of 2031 and 2032.
Restarts are the fastest nuclear additions, and there are only a few candidates. In our view, new reactors with permits are real progress, but they add little before the 2030s.
NRC approval steps · all power-reactor restarts under NRC review and all construction permits issued in 2026 (CPAR-1 to CPAR-3)
| Facility (NRC name) | Action | NRC steps and dates | Source |
|---|---|---|---|
| Palisades Nuclear Plant | Restart | Exemption from license-termination rules: final documentation Jul 24, 2025. Fuel load began Aug 30, 2026. Exigent amendment requested Sep 30, 2026; issued Oct 13, 2026 (Amendment No. 283, recovery of a tilted fuel assembly). | NRC facility page; FR 2026-21594. Licensee: Palisades Energy, LLC |
| Christopher M. Crane Clean Energy Center | Restart | Draft EA/FONSI Jun 8, 2026. Final EA/FONSI dated Sep 18, 2026 (Federal Register Sep 25, 2026). The EA is not the restart approval; NRC expects a decision in 2027. | NRC news release 26-061; FR 2026-19603. Licensee: Constellation Energy Generation, LLC |
| Duane Arnold Energy Center | Restart | Restart licensing actions under NRC review (submittals from Jan 23, 2025); no NRC decision date published. | NRC facility page. Licensee: NextEra Energy Duane Arnold, LLC |
| Kemmerer Power Station Unit 1 | Construction permit | CPAR-1 issued Mar 9, 2026. | FR 2026-05067. Permit holder: US SFR Owner, LLC |
| Clinch River Nuclear Unit 1 | Construction permit | CPAR-2 issued Sep 28, 2026. | FR 2026-20345. Permit holder: Tennessee Valley Authority |
| Long Mott Generating Station | Construction permit | CPAR-3 issued Nov 9, 2026. | FR 2026-23029. Permit holder: Long Mott Energy, LLC |
Dates are NRC issue or document dates; Federal Register publication dates are later. A construction permit allows building, not operation; an operating license is a separate NRC decision.
09 / 12
Planned supply: what is being built, and what counts
Gas plans are large but mostly early-stage. Batteries and solar dominate the near term, and their accredited value is lower per megawatt.
EIA’s monthly plant survey lists about 71 GW of planned gas capacity. About 13 GW of it, roughly 18%, is under construction or finished but not yet operating. Most of the rest has not begun regulatory approval, including 16.1 GW slated for 2030. Planned batteries and solar are larger in the near term: 26.9 GW of batteries and 44.1 GW of solar for 2027.
Not every megawatt counts the same toward reliability. PJM rates each resource class by its expected contribution during risky hours (effective load-carrying capability, ELCC):
Retirements
Supply also leaves. Operators report planned retirements of 7.7 GW for the rest of 2026 (September 2026 survey, so remaining months only), 10.8 GW in 2027 and 15.9 GW in 2028, mostly coal (12.9 GW in 2028). Planned dates often slip. In PJM, every request to retire a unit is posted on its deactivation list; several requests filed in 2026 were later withdrawn, and one listing carries DOE orders.
Nameplate totals overstate firm supply. In our view, the useful question is how much accredited capacity reaches operation by each delivery year, and on current filings the gas share of that is small before 2028.
09 · Planned supply
Most planned gas capacity has not started construction
U.S. planned natural gas generating capacity by planned operating year and EIA status code, GW (nameplate), as of September 2026.
10 / 12
If forecasts run high, who bears the cost?
State regulators are writing minimum bills, long contracts and collateral into large-load tariffs. Region-wide capacity costs still reach every customer.
If forecasts run high, someone pays for lines and plants built for load that never arrives. State regulators have started to put that risk on the large customers that ask for the capacity, through minimum bills, long contracts and collateral (table below).
Capacity prices reach retail bills with a lag, through each state’s default-service auctions. New Jersey’s Board of Public Utilities said its February 2026 auction results “remained relatively flat in part due to the PJM collar,” with typical residential bills changing by between −1.8% and +1.6% by utility, before credits, from June 1, 2026.
Load growth does not always raise prices. An LBNL and Brattle study found that “load growth at the state level has tended to depress retail electricity prices in recent years, by spreading fixed costs over greater load”; in their model, 0.6 cents/kWh lower average prices followed a 10% load increase, with commercial customers benefiting most; residential customers benefited less. The authors warn that “this relationship need not always exist: a higher growth future can increase retail prices if new supply and delivery infrastructure is constrained and costly.” We do not run our own correlation.
These tariffs answer part of the question. In our view, they protect other customers from a single utility’s stranded wires and contracts, but not from region-wide capacity prices, which every customer in a market like PJM pays.
10 · Who pays
Residential prices rose in every state shown
Average residential electricity price, 12 months to August 2026 vs. the prior 12 months, % change. States with large-load tariffs and PJM states.
Large-load terms approved by state regulators · selected
| Regulator (tariff) | Who it covers | Minimum bill | Term | Collateral / exit | Status |
|---|---|---|---|---|---|
| Virginia SCC (GS-5) | 25 MW or more at a site, load factor ≥75% | 85% of contracted transmission and distribution demand (new and existing customers; service before 2016 exempt); 60% of contracted generation demand | 14 years (including up to 4 years of ramp), for contracts from Jan 1, 2027 | Final order: $1.5M/MW, reducible by up to 70% based on the customer’s credit. SCC fact sheet: collateral covers up to 60% of minimum charges over the contract term | Order Nov 25, 2025; effective Jan 1, 2027 |
| PUCO (Schedule DCT) | Data centers of 25 MW or more, AEP Ohio territory | Minimum billing demand is the greater of 85% of the past-11-month peak or a contract-capacity formula, capped at 85% of contract capacity; ramp from 50% of contract capacity in year one | Ramp of up to 4 years plus 8 years (up to 12) | 50% of total minimum charges unless rated A-/A3 and cash over 10× the requirement | Order Jul 9, 2025; effective Jul 23, 2025. Notice of appeal to the Ohio Supreme Court filed Nov 3, 2025 (PUCO docket 24-0508-EL-ATA) |
| IURC (Cause 46097) | 70 MW or more at one site, or 150 MW aggregated (Indiana Michigan Power) | Greater of 80% of contract capacity or 80% of the past-11-month peak | At least 12 years plus a ramp of up to 5 years | May cut contract capacity up to 20% after year five with 42 months’ notice and no exit fee; larger cuts or termination pay an exit fee equal to the remaining minimum charges on that capacity. Collateral required, with a liquidity alternative for unrated customers | Settlement approved as modified, Feb 19, 2025 |
| Georgia PSC (Georgia Power rule) | New customers above 100 MW | Minimum billing allowed (no percentage in the release) | Contracts of up to 15 years (from 5) | Contracts filed with the PSC for review | Approved Jan 23, 2025 |
Sources: Virginia SCC release, final order (PUR-2025-00058) and fact sheet; AEP Ohio Schedule DCT page and PUCO case 24-508-EL-ATA; IURC order and settlement terms; Georgia PSC release. Utilities named only as the tariff holder. Texas is not shown: we have not reviewed final large-load rules under Senate Bill 6.
11 / 12
Reliability: where NERC sees the risk
NERC flags 13 of 23 areas. Five, including PJM and ERCOT, reach high risk by 2029.
NERC’s 2025 assessment finds that 13 of 23 assessment areas face resource adequacy challenges over the next 10 years. In its table, MISO moves to high risk from 2028, and PJM, ERCOT, WECC-Basin and WECC-Northwest from 2029.
NERC’s reasons differ by region. For PJM, it says the anticipated resource margin falls below the reference margin level starting in 2029; for ERCOT, rapid load growth outpaces planned additions in later years even though near-term risk metrics improved.
PJM and ERCOT, the two markets in sections 02 and 04, both move to high risk in 2029. In our view, that is where the forecast question in section 01 becomes a reliability question.
11 · Reliability
NERC rates five areas high risk by 2029
NERC 2025 Long-Term Reliability Assessment, Table 1: capacity and energy risk by assessment area and year, 2026–2030. Areas listed in the table only.
12 / 12
Where the evidence is strong, and what to watch
What the public data support across demand, prices, supply and cost, and the dates that will test it.
Put together, the sections answer our three questions unevenly. Where is the system tightest? Where large loads, thin reserves and slow transmission overlap, which on PJM’s numbers means PJM now, and on NERC’s means both PJM and Texas from 2029. What are prices signaling? In PJM, a capacity market at its cap; in Texas, almost no shortage pricing yet. Who bears the cost if forecasts run high? Increasingly the large customers themselves, at the utility level, but not for region-wide capacity costs.
Inference In our reading, a single capacity market has already priced the gap between forecast demand and firm supply. Whether that price brings supply, or the forecasts come down, is the question for the next two auctions.
Evidence by question · our assessment
| Question | Evidence | Main sources | What it shows |
|---|---|---|---|
| Demand forecasts | Medium | PJM load reports; NERC; EIA | Forecasts rising fast; near-term years revised down in PJM; delivered sales growing more slowly |
| Capacity prices | Strong (PJM) | PJM auction reports | Three auctions at the cap; procured reserves below target |
| Shortage pricing in Texas | Strong (2025 only) | ERCOT market monitor | Almost none in 2025; series ends with the December 2025 market redesign |
| Interconnection | Strong | LBNL | About one in eight requested megawatts reached operation (lower bound) |
| Large-load requests | Medium | ERCOT; FERC | Requests far exceed what qualifies; classifications provisional |
| Transmission and equipment | Medium | FERC staff; DOE; NIAC; BLS | Fewer high-voltage miles; long lead times; prices up |
| New firm supply | Medium | EIA-860M; NRC; PJM ELCC | Little planned gas under construction; restarts slow and few |
| Who pays | Medium | State regulators; LBNL/Brattle | Large-load tariffs shift utility-level risk; region-wide capacity costs remain shared |
Evidence strength is BisonByte’s judgment of how complete and independent the public data are, not a view on any company.
What to watch
FERC orders on large-load tariffs
Responses to the June 18, 2026 show-cause orders were due about mid-August 2026. FERC’s orders on those responses are next.
ERCOT verification
ERCOT is targeting a final community-impact report on December 10, 2026, and Batch Zero classifications are still provisional.
PJM shortfalls
A third straight auction more than one percentage point below the target would trigger a Reliability Backstop Auction.
Nuclear restarts
The NRC expects its restart decision for the Crane Clean Energy Center in 2027.
Planned gas status
Watch EIA-860M each month for gas capacity moving from planned to under construction.
Retail pass-through
Default-service auctions in PJM states show how capacity prices reach households, with a lag.
Related research
BisonByte publishes research for informational purposes only. Nothing on this site constitutes investment advice or an offer or solicitation to buy or sell any security, fund or other financial product; no fund or investment product is offered through this site. Content on this site has not been reviewed by any regulator. Data come from sources believed to be reliable but are not guaranteed, and views may change without notice. See our full Disclosures.