Research  /  Energy & Power

Energy & Power

U.S. electricity demand is growing again, and data centers are emerging as the main driver. This page follows the evidence from forecasts to prices, the interconnection queue, the wires and the fuel, and asks three questions: where is the system tightest, what are prices signaling, and who bears the cost if forecasts run high?

BisonByte Research · Data as of November 20, 2026 · Every chart links its sources

$28.92 → $325
PJM capacity price, $/MW-day (RTO, UCAP), 2024/25 to 2028/29. Cleared at the cap in all three auctions under the price collar (2026/27–2028/29). The collar is fixed in ICAP terms (cap $256.75, floor $138.25 per MW-day); for 2028/29 that was about $175–$325 in UCAP terms (approximate; varies by auction).
6.8 GW
Capacity PJM’s 2028/29 auction procured below its reliability requirement, even at the cap.
13%
Share of capacity requesting interconnection in 2000–2020 that was operating by end-2025 (LBNL, by capacity; a lower bound, as 10% is still active).
132 → 224 GW
NERC’s 10-year summer peak growth forecast, 2024 vs 2025 assessment (North America, sum of assessment areas).

01  /  12

Demand: forecasts are rising faster than sales

Sales are growing again. Grid forecasts for the next decade have grown much faster, and they are being revised in both directions.

After a long plateau, U.S. electricity use is rising again. EIA reports retail sales of 4,080 terawatt-hours in 2025, up from 3,975 in 2024, and its short-term outlook forecasts 4,171 for 2026 and 4,232 for 2027. In the 2026 Annual Energy Outlook, EIA says demand rose 2.1% a year over the past five years and projects 0.9%–1.6% a year through 2050, and says data center load “is emerging as the dominant driver of long-term U.S. electricity growth.”

Commercial customers now buy more power than households. In the 12 months to August 2026, commercial sales were 1,536.9 TWh against 1,526.4 TWh residential (2026 months are preliminary).

Grid planners have moved further. NERC now expects summer peak demand across North America to rise by 224 GW over 10 years, up from 132 GW a year earlier and over 80 GW in the 2023 assessment. These are sums of NERC assessment areas, including Canada, not U.S.-only figures. In PJM, each annual forecast has raised the 10-year increase, from about 12 GW in the 2023 report to about 66 GW in the 2026 report.

The 2026 report also cut the near term: PJM says it is “lower than the 2025 Long-Term Load Forecast in the near term through 2032 due to updates to the electric vehicle forecast, economics and large load adjustments.” Both can be true because the windows differ and because later years now carry more large-load growth. For data-center demand ranges from LBNL and the IEA, see our AI & Compute page.

Our view

Forecasts are rising faster than delivered sales. In our view, the gap between what planners expect and what customers have committed to is the main uncertainty on this page; sections 04 and 10 show how regulators are trying to narrow it.

01 · Demand

Each PJM forecast has raised the 10-year outlook

PJM RTO summer peak: forecast increase over each report’s 10-year horizon, GW, by report year.

BISONBYTE RESEARCHSource: PJM Load Forecast Reports 2023; 2024; 2025; 2026. Data as of November 20, 2026. Notes: Each report starts from a different base year, so the bars cover different 10-year windows. A bigger 10-year increase can sit alongside a lower near-term forecast: the 2026 report is below the 2025 report through 2032, then higher later in its horizon.

02  /  12

Prices: a capacity market at its cap

PJM’s forward capacity price has hit its cap three times. Texas showed almost no shortage pricing in 2025. The two measure different things.

PJM, the grid operator for much of the Mid-Atlantic and Midwest, runs an auction that buys capacity ahead of each delivery year. Its RTO price rose from $28.92 per MW-day for 2024/25 to $269.92 for 2025/26. A price collar (cap $256.75, floor $138.25 per MW-day ICAP; about $325–$333 and $175–$180 in UCAP terms) applied to the 2026/27–2028/29 auctions, and all three cleared at the cap: $329.17, $333.44 and $325.00.

Even at the cap, the 2028/29 auction procured 6,831.3 MW less than PJM’s reliability requirement, close to the prior auction’s 6,516 MW. PJM’s own reading: “Such a shortage does not necessarily mean that the PJM system will be unable to serve load reliably… it means that PJM would have to operate with slimmer reserves.” Under the tariff, a shortfall of more than one percentage point below the target for three auctions in a row triggers a Reliability Backstop Auction; 2028/29 was the second in a row.

Texas shows a different pattern. ERCOT’s market monitor reports that its real-time shortage adder (ORDC) added about $0.02/MWh on average in 2025, the lowest since 2014, as solar and battery additions raised reserves. The all-in price rose from almost $34 to $38/MWh (+13.8%), driven mainly by a 61% rise in gas prices, not scarcity. Since real-time co-optimization went live on December 5, 2025, shortage pricing is embedded in energy prices, so this adder series ends in 2025.

We do not chart wholesale energy prices side by side. EIA’s republished ICE hub data trade different products at the two hubs (PJM West real-time peak, ERCOT North 345 kV peak), and the ERCOT North series has no trades after 2019, so a fair comparison is not possible from that source.

Our view

Inference The two largest data-center regions price scarcity differently. PJM’s forward capacity auction has cleared at its cap three times; ERCOT’s energy-only market showed almost no realized shortage pricing in 2025. The two numbers measure different things (a forward capacity price vs. realized real-time adders), and ERCOT’s monitor warns the current surplus could erode quickly as large loads connect.

02 · Prices

PJM’s capacity price has cleared at its cap three auctions in a row

PJM Base Residual Auction, RTO clearing price by delivery year, $/MW-day of unforced capacity (UCAP).

BISONBYTE RESEARCHSource: PJM BRA reports: 2028/29; 2027/28; 2026/27; 2025/26 (with history). Data as of November 20, 2026. Notes: RTO price only; some zones cleared higher (2025/26: BGE $466.35, Dominion $444.26). The collar is fixed in ICAP terms (cap $256.75, floor $138.25 per MW-day), so its UCAP value differs by auction. The 2027/28 and 2028/29 auctions ran about 23 months ahead of delivery instead of the usual three years.
14.7% vs 20.0%
Procured reserve margin (RPM+FRR, PJM estimate) vs the installed reserve margin (IRM) target, 2028/29
PJM 2028/29 BRA report
14.9%
Same measure, 2027/28, against a 20.0% target
PJM 2027/28 BRA report
$554.72
PJM’s simulated 2028/29 RTO price without the collar ($/MW-day UCAP)
PJM 2028/29 BRA report

03  /  12

Interconnection: the queue is long, and most of it never gets built

Supply additions depend on getting through the queue. Historically, about one in eight requested megawatts has made it.

New supply has to pass through an interconnection queue before it can run. LBNL finds that “only 13% of capacity that submitted interconnection requests from 2000-2020 had reached commercial operations by the end of 2025;” 75% was withdrawn and 10% is still active. That makes 13% a lower bound.

The queue itself is changing mix. At the end of 2025, more than 2,060 GW was actively seeking connection. Active natural gas capacity rose 86% to 253 GW in 2025, while solar, storage and wind fell.

Our view

A long queue is not a supply pipeline. In our view, a completion rate of about one in eight (13%), by capacity, is the right discount to apply when reading any headline queue total.

03 · Interconnection

Most capacity that asks to connect never gets built

Status at end-2025 of generation and storage capacity that requested interconnection, by request year, % of MW.

BISONBYTE RESEARCHSource: LBNL, Queued Up 2026 (data through 2025). Data as of November 20, 2026. Notes: BisonByte calculation from the LBNL project file; shares by capacity. Recent cohorts have had less time to finish, so their operating shares will rise.

Share of 2000–2020 requests operating by end-2025, by type (MW)

Resource typeOperating
Natural gas17%
Nuclear18%
Wind16%
Solar11%
Solar+Battery9%
Battery7%

BisonByte calculation from the LBNL project-level file. Lower bound: some capacity is still active.

04  /  12

Large loads: the requests far exceed what will connect

Texas and federal regulators are sorting real projects from speculative ones, and rewarding loads that can be flexible.

ERCOT paused approvals to energize new data centers and crypto-mining loads of 75 MW or more (Aug 3, 2026) pending a verification audit; provisional Batch Zero classification (Sep 3, 2026): 66.4 GW base, 127.9 GW studied, 302.2 GW excluded (BisonByte sum ≈497 GW).

ERCOT’s November community-impact survey drew responses covering about 177 GW of requested capacity; 33 projects each requesting more than 1 GW together account for 36% of requested capacity, and West Texas holds 41%. ERCOT is targeting a final report on December 10, 2026.

Federal rules are moving too:

Oct 23, 2025DOE directs FERC to consider a large-load interconnection rulemaking (ANOPR); large loads are “generally defined as electricity demand greater than 20 megawatts.”
Apr 16, 2026FERC says it intends to act on the docket by the end of June 2026.
Jun 18, 2026FERC orders the six grid operators under its jurisdiction (PJM, MISO, SPP, CAISO, ISO-NE, NYISO) to justify their tariffs or file large-load provisions within 60 days, and to report on resource adequacy within 30 days. ERCOT is not FERC-jurisdictional.
Aug 3, 2026Texas: after a Governor’s directive, ERCOT pauses approvals to energize new data centers and crypto-mining loads of 75 MW or more pending a verification audit.

Flexible loads

Several rule changes would let large loads connect sooner if they agree to curtail. FERC’s June orders list “new transmission services for flexible large loads” among five reform areas, and the DOE proposal asks whether flexible loads could be studied within 60 days. In Texas, Senate Bill 6 (2025) created a Large Load Demand Management Service; ERCOT’s market monitor expects its rulemaking to finish in 2026. In PJM, a September 2025 proposal for “non-capacity-backed load” (new large loads that would not pay for capacity and could be curtailed before capacity-backed demand response) was described as withdrawn by Maryland’s Office of People’s Counsel in October 2025; in January 2026 the PJM Board directed work on a “Connect and Manage” approach instead: new large loads that do not bring their own new generation would be curtailed before emergency demand response when load shed is needed, loads that do bring generation get an expedited interconnection track, and PJM is to start a reliability backstop procurement.

Our view

Request totals mix firm projects with speculative ones. In our view, the share that survives verification, not the headline request, is the number that matters for forecasts and for who pays (section 10).

04 · Large loads

Most of Texas’s large-load requests did not qualify for the first study

ERCOT Batch Zero: provisional classification of large-load requests, GW, as of September 3, 2026.

BISONBYTE RESEARCHSource: ERCOT Board, Batch Zero update (Sep 11, 2026). Data as of November 20, 2026. Notes: Provisional (conditional) classification. The total of about 497 GW is a BisonByte sum; ERCOT does not publish one. An ERCOT chart of studied load by year shows 125.4 GW, which may exclude loads after 2032; we use 127.9 GW from the text.

05  /  12

Transmission: fewer high-voltage miles

Line additions fell by more than half in 2025, mostly at the highest voltages.

New generation and new loads both need wires. FERC staff count 782.9 miles of new transmission completed in 2025, less than half of the 1,697.4 miles in 2024. The drop is concentrated at the highest voltages: 500 kV-class additions fell from 554.0 miles to 1.8, while 345 kV rose from 352.1 to 400.8.

FERC staff list 1,838.4 miles as high-probability additions through May 2028, out of 2,202.4 miles proposed.

Our view

Line miles are a blunt measure, but the direction matters. In our view, high-voltage transmission is the slowest piece to change, so it is likely to set where large loads can connect first.

05 · Transmission

High-voltage line additions fell sharply in 2025

Miles of new U.S. transmission lines completed by voltage class, 2024 and 2025, and high-probability additions through May 2028.

BISONBYTE RESEARCHSource: FERC Energy Infrastructure Update, December 2025. Data as of November 20, 2026. Notes: Based on NERC data as compiled by FERC staff. Annual totals are lumpy: one or two long 500 kV projects can swing a year. Miles of line, not transfer capacity.

06  /  12

Grid equipment: long waits, higher prices

Transformer lead times are quoted in years, and producer prices have nearly doubled since 2020.

Large power transformers are a common bottleneck. The Department of Energy reported in 2024 that lead times have become exceptionally long, “with 36-month lead times being commonly quoted and maximum lead times reaching as much as 60 months.” The National Infrastructure Advisory Council cited Wood Mackenzie data showing average transformer lead times rising from about 50 weeks in 2021 to about 120 weeks in 2024, and 80–210 weeks for large substation and generator step-up units (Wood Mackenzie data as cited by NIAC).

No free public series tracks lead times month by month, so the chart shows the closest official proxy: producer prices. The index rose from 255.5 in January 2020 to 483.9 in October 2026 (preliminary). Copper is another input: USGS estimates U.S. net import reliance at 57% of consumption in 2025.

Three turbine makers each report record order books, on definitions that are not comparable (with or without reservations, steam turbines, or frame size), so we do not compare them. Section 09 uses EIA’s plant-level data instead.

Our view

Higher prices and long waits point the same way. In our view, equipment, not only permits, will pace how fast new lines and substations arrive.

06 · Grid equipment

Transformer producer prices are up about 89% since January 2020

BLS Producer Price Index, power, distribution and specialty transformer manufacturing (PCU335311335311), monthly, January 2018 to October 2026.

BISONBYTE RESEARCHSource: BLS PPI series PCU335311335311. Data as of November 20, 2026. Notes: This index measures producer prices, not lead times. October 2026 is preliminary.

07  /  12

Fuel: gas carries the load, and LNG competes for it

Gas makes about 40% of U.S. power. Exports are rising at the same time, and pipelines set how fast supply can move.

Natural gas is the largest source of U.S. power. EIA puts its share of generation at 39.9% in 2025 and forecasts close to 40% in 2026 and 2027. Gas burned for power has held around 36–38 Bcf/d since 2024, while LNG exports rose from 11.9 Bcf/d in 2024 to 15.1 in 2025 and 17.3 so far in 2026. Henry Hub averaged $2.19 in 2024 and $3.53 in 2025.

EIA’s November outlook expects LNG exports of 19.0 Bcf/d in 2027 and a Henry Hub price near $2.88 in 2027, down from about $3.37 in 2026.

Pipelines are the delivery constraint. EIA’s pipeline project list shows 35 projects under construction (33 with stated capacity), with a sum of stated additional capacity of about 41 Bcf/d, and 13 on hold.

Our view

Power demand and LNG exports are now pulling on the same supply. In our view, gas prices, not scarcity, explained most of the 2025 rise in Texas power costs, and the same link will shape costs elsewhere.

07 · Fuel

Power and LNG are both drawing more gas

U.S. natural gas burned for power and LNG exports, Bcf/d (bars), and Henry Hub spot price, $/MMBtu (line), annual averages.

BISONBYTE RESEARCHSource: EIA Henry Hub spot; EIA LNG exports; EIA gas delivered to electric power. Data as of November 20, 2026. Notes: *2026 is year to date: LNG and power burn through August, Henry Hub through October. Annual values are BisonByte means of EIA monthly data.

08  /  12

Nuclear: restarts first, new reactors later

A complete list of restarts under NRC review and of 2026 construction permits, with the approval steps each has passed.

Nuclear supply can grow three ways: uprates, restarts and new reactors. The table lists every power-reactor restart under NRC review and every construction permit the NRC issued in 2026. One restart has loaded fuel; a second has a final environmental assessment, with the NRC’s restart decision expected in 2027 for the 800-plus megawatt unit.

Fuel is a constraint for many advanced designs. DOE says “HALEU is not currently available from domestic suppliers.” It has made conditional allocations of high-assay low-enriched uranium in three rounds: April 9, 2025 (5 recipients), August 26, 2025 (3) and July 23, 2026 (2, including NASA).

EIA’s plant-level data show planned nuclear additions of 0.5 GW in 2030 and 2.2 GW in each of 2031 and 2032.

Our view

Restarts are the fastest nuclear additions, and there are only a few candidates. In our view, new reactors with permits are real progress, but they add little before the 2030s.

NRC approval steps · all power-reactor restarts under NRC review and all construction permits issued in 2026 (CPAR-1 to CPAR-3)

Facility (NRC name)ActionNRC steps and datesSource
Palisades Nuclear PlantRestartExemption from license-termination rules: final documentation Jul 24, 2025. Fuel load began Aug 30, 2026. Exigent amendment requested Sep 30, 2026; issued Oct 13, 2026 (Amendment No. 283, recovery of a tilted fuel assembly).NRC facility page; FR 2026-21594. Licensee: Palisades Energy, LLC
Christopher M. Crane Clean Energy CenterRestartDraft EA/FONSI Jun 8, 2026. Final EA/FONSI dated Sep 18, 2026 (Federal Register Sep 25, 2026). The EA is not the restart approval; NRC expects a decision in 2027.NRC news release 26-061; FR 2026-19603. Licensee: Constellation Energy Generation, LLC
Duane Arnold Energy CenterRestartRestart licensing actions under NRC review (submittals from Jan 23, 2025); no NRC decision date published.NRC facility page. Licensee: NextEra Energy Duane Arnold, LLC
Kemmerer Power Station Unit 1Construction permitCPAR-1 issued Mar 9, 2026.FR 2026-05067. Permit holder: US SFR Owner, LLC
Clinch River Nuclear Unit 1Construction permitCPAR-2 issued Sep 28, 2026.FR 2026-20345. Permit holder: Tennessee Valley Authority
Long Mott Generating StationConstruction permitCPAR-3 issued Nov 9, 2026.FR 2026-23029. Permit holder: Long Mott Energy, LLC

Dates are NRC issue or document dates; Federal Register publication dates are later. A construction permit allows building, not operation; an operating license is a separate NRC decision.

09  /  12

Planned supply: what is being built, and what counts

Gas plans are large but mostly early-stage. Batteries and solar dominate the near term, and their accredited value is lower per megawatt.

EIA’s monthly plant survey lists about 71 GW of planned gas capacity. About 13 GW of it, roughly 18%, is under construction or finished but not yet operating. Most of the rest has not begun regulatory approval, including 16.1 GW slated for 2030. Planned batteries and solar are larger in the near term: 26.9 GW of batteries and 44.1 GW of solar for 2027.

Not every megawatt counts the same toward reliability. PJM rates each resource class by its expected contribution during risky hours (effective load-carrying capability, ELCC):

59%
4-hour storage
PJM ELCC, 2028/29
10%
Tracking solar
PJM ELCC, 2028/29
34%
Onshore wind
PJM ELCC, 2028/29
78%
Gas combined cycle
PJM ELCC, 2028/29
67%
Gas combustion turbine
PJM ELCC, 2028/29
96%
Nuclear
PJM ELCC, 2028/29

Retirements

Supply also leaves. Operators report planned retirements of 7.7 GW for the rest of 2026 (September 2026 survey, so remaining months only), 10.8 GW in 2027 and 15.9 GW in 2028, mostly coal (12.9 GW in 2028). Planned dates often slip. In PJM, every request to retire a unit is posted on its deactivation list; several requests filed in 2026 were later withdrawn, and one listing carries DOE orders.

Our view

Nameplate totals overstate firm supply. In our view, the useful question is how much accredited capacity reaches operation by each delivery year, and on current filings the gas share of that is small before 2028.

09 · Planned supply

Most planned gas capacity has not started construction

U.S. planned natural gas generating capacity by planned operating year and EIA status code, GW (nameplate), as of September 2026.

BISONBYTE RESEARCHSource: EIA-860M, September 2026. Data as of November 20, 2026. Notes: BisonByte aggregation of the Planned sheet. Status codes: P planned, regulatory approvals not initiated; L approvals pending; T approvals received, not under construction; U/V under construction (up to or over 50% complete); TS construction complete, not yet operating. Covers reported units of 1 MW or more. A further 1.8 GW planned for 2034 is not shown.

10  /  12

If forecasts run high, who bears the cost?

State regulators are writing minimum bills, long contracts and collateral into large-load tariffs. Region-wide capacity costs still reach every customer.

If forecasts run high, someone pays for lines and plants built for load that never arrives. State regulators have started to put that risk on the large customers that ask for the capacity, through minimum bills, long contracts and collateral (table below).

Capacity prices reach retail bills with a lag, through each state’s default-service auctions. New Jersey’s Board of Public Utilities said its February 2026 auction results “remained relatively flat in part due to the PJM collar,” with typical residential bills changing by between −1.8% and +1.6% by utility, before credits, from June 1, 2026.

Load growth does not always raise prices. An LBNL and Brattle study found that “load growth at the state level has tended to depress retail electricity prices in recent years, by spreading fixed costs over greater load”; in their model, 0.6 cents/kWh lower average prices followed a 10% load increase, with commercial customers benefiting most; residential customers benefited less. The authors warn that “this relationship need not always exist: a higher growth future can increase retail prices if new supply and delivery infrastructure is constrained and costly.” We do not run our own correlation.

Our view

These tariffs answer part of the question. In our view, they protect other customers from a single utility’s stranded wires and contracts, but not from region-wide capacity prices, which every customer in a market like PJM pays.

10 · Who pays

Residential prices rose in every state shown

Average residential electricity price, 12 months to August 2026 vs. the prior 12 months, % change. States with large-load tariffs and PJM states.

BISONBYTE RESEARCHSource: EIA HS861M monthly state data. Data as of November 20, 2026. Notes: BisonByte calculation: total residential revenue divided by sales over each 12-month window. 2026 months are preliminary. Prices reflect fuel, delivery, capacity and policy costs; this chart does not attribute any change to data centers.

Large-load terms approved by state regulators · selected

Regulator (tariff)Who it coversMinimum billTermCollateral / exitStatus
Virginia SCC (GS-5)25 MW or more at a site, load factor ≥75%85% of contracted transmission and distribution demand (new and existing customers; service before 2016 exempt); 60% of contracted generation demand14 years (including up to 4 years of ramp), for contracts from Jan 1, 2027Final order: $1.5M/MW, reducible by up to 70% based on the customer’s credit. SCC fact sheet: collateral covers up to 60% of minimum charges over the contract termOrder Nov 25, 2025; effective Jan 1, 2027
PUCO (Schedule DCT)Data centers of 25 MW or more, AEP Ohio territoryMinimum billing demand is the greater of 85% of the past-11-month peak or a contract-capacity formula, capped at 85% of contract capacity; ramp from 50% of contract capacity in year oneRamp of up to 4 years plus 8 years (up to 12)50% of total minimum charges unless rated A-/A3 and cash over 10× the requirementOrder Jul 9, 2025; effective Jul 23, 2025. Notice of appeal to the Ohio Supreme Court filed Nov 3, 2025 (PUCO docket 24-0508-EL-ATA)
IURC (Cause 46097)70 MW or more at one site, or 150 MW aggregated (Indiana Michigan Power)Greater of 80% of contract capacity or 80% of the past-11-month peakAt least 12 years plus a ramp of up to 5 yearsMay cut contract capacity up to 20% after year five with 42 months’ notice and no exit fee; larger cuts or termination pay an exit fee equal to the remaining minimum charges on that capacity. Collateral required, with a liquidity alternative for unrated customersSettlement approved as modified, Feb 19, 2025
Georgia PSC (Georgia Power rule)New customers above 100 MWMinimum billing allowed (no percentage in the release)Contracts of up to 15 years (from 5)Contracts filed with the PSC for reviewApproved Jan 23, 2025

Sources: Virginia SCC release, final order (PUR-2025-00058) and fact sheet; AEP Ohio Schedule DCT page and PUCO case 24-508-EL-ATA; IURC order and settlement terms; Georgia PSC release. Utilities named only as the tariff holder. Texas is not shown: we have not reviewed final large-load rules under Senate Bill 6.

11  /  12

Reliability: where NERC sees the risk

NERC flags 13 of 23 areas. Five, including PJM and ERCOT, reach high risk by 2029.

NERC’s 2025 assessment finds that 13 of 23 assessment areas face resource adequacy challenges over the next 10 years. In its table, MISO moves to high risk from 2028, and PJM, ERCOT, WECC-Basin and WECC-Northwest from 2029.

NERC’s reasons differ by region. For PJM, it says the anticipated resource margin falls below the reference margin level starting in 2029; for ERCOT, rapid load growth outpaces planned additions in later years even though near-term risk metrics improved.

Our view

PJM and ERCOT, the two markets in sections 02 and 04, both move to high risk in 2029. In our view, that is where the forecast question in section 01 becomes a reliability question.

11 · Reliability

NERC rates five areas high risk by 2029

NERC 2025 Long-Term Reliability Assessment, Table 1: capacity and energy risk by assessment area and year, 2026–2030. Areas listed in the table only.

Assessment area
2026
2027
2028
2029
2030
MISO
N
E
H
H
H
MRO-Manitoba
N
N
N
E
E
MRO-SaskPower
E
E
N
N
N
MRO-SPP
E
E
E
E
E
NPCC-Maritimes
E
E
E
E
E
NPCC-New England
N
N
N
E
E
NPCC-New York
E
E
E
E
E
NPCC-Quebec
N
N
N
E
E
PJM
E
E
E
H
H
SERC-East
N
E
E
E
E
Texas RE-ERCOT
E
E
E
H
H
WECC-Basin
E
E
E
H
H
WECC-Northwest
N
N
N
H
H
HighElevatedNormal
BISONBYTE RESEARCHSource: NERC 2025 LTRA, Table 1. Data as of November 20, 2026. Notes: Transcribed by BisonByte from the color-coded table (H = high, E = elevated, N = normal). The table lists the 13 of 23 areas NERC flags as facing challenges; the other areas are not shown. Includes Canadian areas.

12  /  12

Where the evidence is strong, and what to watch

What the public data support across demand, prices, supply and cost, and the dates that will test it.

Put together, the sections answer our three questions unevenly. Where is the system tightest? Where large loads, thin reserves and slow transmission overlap, which on PJM’s numbers means PJM now, and on NERC’s means both PJM and Texas from 2029. What are prices signaling? In PJM, a capacity market at its cap; in Texas, almost no shortage pricing yet. Who bears the cost if forecasts run high? Increasingly the large customers themselves, at the utility level, but not for region-wide capacity costs.

Our view

Inference In our reading, a single capacity market has already priced the gap between forecast demand and firm supply. Whether that price brings supply, or the forecasts come down, is the question for the next two auctions.

Evidence by question · our assessment

QuestionEvidenceMain sourcesWhat it shows
Demand forecastsMediumPJM load reports; NERC; EIAForecasts rising fast; near-term years revised down in PJM; delivered sales growing more slowly
Capacity pricesStrong (PJM)PJM auction reportsThree auctions at the cap; procured reserves below target
Shortage pricing in TexasStrong (2025 only)ERCOT market monitorAlmost none in 2025; series ends with the December 2025 market redesign
InterconnectionStrongLBNLAbout one in eight requested megawatts reached operation (lower bound)
Large-load requestsMediumERCOT; FERCRequests far exceed what qualifies; classifications provisional
Transmission and equipmentMediumFERC staff; DOE; NIAC; BLSFewer high-voltage miles; long lead times; prices up
New firm supplyMediumEIA-860M; NRC; PJM ELCCLittle planned gas under construction; restarts slow and few
Who paysMediumState regulators; LBNL/BrattleLarge-load tariffs shift utility-level risk; region-wide capacity costs remain shared

Evidence strength is BisonByte’s judgment of how complete and independent the public data are, not a view on any company.

What to watch

FERC orders on large-load tariffs

Responses to the June 18, 2026 show-cause orders were due about mid-August 2026. FERC’s orders on those responses are next.

ERCOT verification

ERCOT is targeting a final community-impact report on December 10, 2026, and Batch Zero classifications are still provisional.

PJM shortfalls

A third straight auction more than one percentage point below the target would trigger a Reliability Backstop Auction.

Nuclear restarts

The NRC expects its restart decision for the Crane Clean Energy Center in 2027.

Planned gas status

Watch EIA-860M each month for gas capacity moving from planned to under construction.

Retail pass-through

Default-service auctions in PJM states show how capacity prices reach households, with a lag.

Related research

AI & ComputeChips, data centers and the demand ranges behind section 01.Robotics & AutonomyMachines that sense and move, from factory robots to robotaxis.
Computational BiologyComing soon.
MethodEvery number on this page comes from a regulator, grid operator, market monitor, statistical agency, national lab or utility tariff, linked in the text or under each chart.

Independent, primary-data research on the technologies reshaping the economy.

BisonByte publishes research for informational purposes only. Nothing on this site constitutes investment advice or an offer or solicitation to buy or sell any security, fund or other financial product; no fund or investment product is offered through this site. Content on this site has not been reviewed by any regulator. Data come from sources believed to be reliable but are not guaranteed, and views may change without notice. See our full Disclosures.

© 2026 BisonByte. All rights reserved.  ·  Contact: info@bisonbyte.ai